Eiffel Tower At Paris Las Vegas

An incredible mix of art and architecture, the Eiffel Tower remains one of the most recognized and visited structures in the world, averaging more than six million visitors each year. The Eiffel Tower is certainly synonymous with Paris, as the Statue of Liberty is with New York, the Acropolis with Greece and the Taj Mahal with India. So when plans were in motion to construct a ½ scale, 540-foot replica of the Eiffel Tower in Las Vegas, the owners certainly recognized and appreciated the attention to detail and the high profile characteristics that the job would bring.

“Las Vegas is a city that never sleeps,” said Tnemec coating consultant Tony Hobbs. “The project required a practical application solution with excellent weathering and corrosion characteristics and that would allow contractors to spray upwards of five hundred feet in the air. We certainly did not want to end up painting the town.”

Four variations of a bronze color were specified for the 5,000 tons of welded steel. Series 90-97 Tneme-Zinc, a two-component, moisture-cured, zinc-rich primer known for its long-term corrosion benefits, was specified for the exterior steel of the tower and was key to the long-term corrosion protection of the steel. Following abrasive blasting in accordance with SSPC-SP6/NACE No. 3 Commercial Blast, the steel was shop-primed with Series 90-97 Tneme-Zinc, a zinc-rich urethane, and transported to the job site in Las Vegas.

Touch-up of the primer was done on site, along with the topcoat application of Series 113 H.B. Tneme-Tufcoat. A high-build, low-odor waterborne acrylic epoxy, it has excellent exterior weathering capabilities along with fade-resistant coloring properties. In this case, the high-build spray characteristics of Series 113 allowed for one finish coat, saving costs on a project of this size. “The Tnemec coating system specified was economical and provided the high quality corrosion protection that was required,” noted Hobbs. “The project still looks good to this day.”

    Project Information

    Location
    Las Vegas, Nevada

    Completion
    June 1998

    Owner
    Hilton Hotel (former) & Harrah's Entertainment

    Architecture
    Leidenfrost/Horowitz & Associates, Inc., Glendale, CA

    Field Applicator
    Robinson-Prezioso, Inc. of Santa Fe Springs, California

    Fabricator
    Schuff Steel Company, Phoenix, AZ

    Printer Friendly Version

    PP_Eiffel_Tower_Profile

    Contact Your Rep

    Looking for Some Local Coatings Guidance?

    Reach out to one of our knowledgable and reliable representatives near you.

    How to Purchase

    Ready to Order Tnemec?

    We're ready to help. Click below to learn more about our purchasing process.

    Sustainable Building

    Need Coatings for LEED Projects?

    Tnemec offers a long list of low VOC coatings built to protect sustainable structures.

    Continue Exploring in the color tool

    Close

    Color Swatch packet

    When you finish selecting, request your Swatch Packet below. Expect your swatch cards in 5-7 business days. Contact your expert Sales Rep at any time.

    Sorry, there is a maximum of 6 color swatches.

    Request swatch packet

    Continue Exploring in the color tool

    Close