The northern lagoon of Bixby, Okla., is exposed to more than just the usual weather elements: sun, wind, rain, snow, etc. In fact, the concrete structure is also exposed to impact and abrasion as well as high levels of hydrogen sulfide (H2S) gas and other chemicals, making the coating selection and application particularly challenging and important.

In 2002 when the city decided to construct the headworks structure for the lagoon, another product had been recommended. However, after further review planners decided to instead install a then relatively new Tnemec product, Series 434 Perma-Shield H2S. This aggregate-reinforced, 100% solids epoxy mortar is designed for wastewater immersion/fume environments where H2S and sulfuric acid are present.Bixby North Lagoon Headworks Expansion Bixby North Lagoon Headworks coatings application

Series 201 Epoxoprime, a 100% solids moisture-tolerant epoxy, was first used to prime the concrete prior to the Perma-Shield H2S application. For additional protection, a glaze coat of Series 435 Perma-Glaze was then applied. A versatile, thick film, 100% solids, abrasion-resistant lining, Perma-Glaze provides low permeation to H2S gas, protects against MIC and provides additional chemical resistance to severe wastewater environments.

In early 2007, nearly five years after completion, the products are performing as hoped and continue to withstand the effects of impact, abrasion and corrosion of the concrete.

project information

Project Name

Bixby North Lagoon Expansion

Project Completion Date

August 2002

Engineer

Crafton Tull Associates, Tulsa, OK

Project Location

Bixby, OK

Owner

City of Bixby

Field Applicator

Luckinbill, Enid, OK